Reactivate lines

Top  Previous  Next

Production lines that have been previously deactivated may be reactivated and made available for production.  In order to reactivate a second-shift line, a first-shift line must be available or in the process of being reactivated.  Both first and second-shift lines may be reactivated at the same time.  The number of lines available for reactivation, if any, are shown in the Production Capacity Status section of your Operating Information Report.

Reactivation requires one quarter of preparation before a line may be scheduled for production.  Enter the number of lines to be reactivated under the appropriate area on the decision form. Lines may not be scheduled for production until the following quarter.

Limits:  0 to number of lines previously deactivated

Note:  A second-shift line must be supported by a first-shift line.  You may not reactivate a second-shift line unless you have a supporting first-shift line either available, being built or reactivated.